Restoration

Latest Restoration – 2019

We have just completed a major project to strengthen six of the primary columns that support the hundreds of tons of machinery that remain in the shaft-rock house. The work was conducted by a skilled crew from REJ Contracting. The $22,000 project took about four weeks to complete.
Making the support column repairs a priority was based on the results of the 2018 Structural Survey by George Kiiskila (UP Engineering). It was recommended that 4-5 foot sections of six support columns be strengthened with new steel. These sections of the columns were buried in damp rock dust. The corrosion to the steel was significant enough to threaten the structure’s ability to support the crushing machinery still in the shaft-rock house above.Before work on the columns could begin the two ore bins (North and South Chambers) located below the crushers needed to be mucked out. This job took four men four days to complete.
The bottom of the bins contained over 200 cubic yards of rock dust which had accumulated over the 65 years that the mine was in operation. Workers reported that this compacted dust was “as hard as concrete” and very difficult to break up.
Adams Township allowed us to tap into a nearby fire hydrant. The powerful water stream allowed workers to flush the muck down the ore chutes. Once the area around the base of the support columns was cleared, repair work could begin.
First the rotten steel was ground down to a fresh metal surface. Next 400 pounds of new 3/4” plate steel was welded onto what remained of the old steel. A rebar web was then welded to the base area of the new steel. This steel would transfer the load from the column to the concrete poured in the next step. In the final step concrete was poured around the base of the column. This concrete sits on the original massive foundation under the shaft-rock house.
The weight of the crushing machinery is now safely supported by good steel on a solid foundation.

A new door has also been installed on the Captain’s office.

 

Future restorations

Future restoration plans include an environmental study to recommend a plan of action to clean up any  environmental hazzards in the site, such as asbestos.

Our long range plans include creating a plaque/wall to honor the miners who died in the mines, and restoring the shaft house, Captain’s office, and hoist house and opening them as a museum.

 

Previous Restorations

 

2018


REJ Contracting worked to provide safe access to the upper reaches of the mineshaft for a structural engineering study (completed by George Kiiskila of UP Engineers and Architects. REJ Contracting also buttoned up problem leaking areas of the mineshaft roofing, secured the lower corrugated metal perimeters of the shaft where intruders were making their own access to the shaft, replaced sections of the sheathing as needed and secured the loose sheathing at the top of the headframe, covering the window way up there, to prevent the piece of metal becoming a projectile in high winds. A man door to the shaft house was also secured.

The floor of the mineshaft was leveled with poor rock from the poor rock pile nearby. The extra poor rock was used outside to make a smoother walking access over the rather steep drop to the lower level of the mineshaft/rockhouse with a handrail installed for safety. In addition, broken windows were replaced with plexiglass.

We also repaired the roof on the Captain’s office.

Fall 2017

Safety of the shaft house, over the years, has been an ongoing concern. Until this fall, the materials car, estimated as weighing 2-3 tons, was still suspended from the gantry in the shaft house. Hanging by a heavy duty iron link chain, it was a possible safety hazard due to deterioration of the supporting gantry structure over the years of non-use and exposure to the forces of nature/weather/moisture. The Houghton County Mine Inspector recommended alleviating this concern by either building a supporting structure underneath the car, or letting it down to reside on its back in the shaft house on a support made from pressure treated timbers. Proceeding with further work planned in the shaft house, depended first on the alleviation of the materials car safety problem. After carefully considering all suggestions and options for this project, it was decided that the best decision for safety and preservation was to lower the car.

The inside of the shafthouse shows the large materials car lowered.

Materials Car

Summer 2016

We are excited to announce that we have made the Captain’s office handicap accessible. We now have a concrete parking area on the side of the building with a ramp going to the back of the building to accommodate a wheelchair. The front of the building was not an option, as that entrance is not as close to the ground and there is a small shed attached to the building which would be difficult to maneuver a wheel chair.

Phase 4


Painesdale Mine & Shaft, Inc. is pleased to announce that we have completed phase 4 of the Save Our Shaft House project. We have recently restored the windows of the shaft house to their original condition. We have also repaired/replaced the steps going to the Captain’s office.

New windows on the shaft house

New windows

Phase 3


In the late 1990’s, the main waterline from Painesdale to Hancock burst somewhere in the vicinity of  Champion #4. As a result, the middle columns of the shaft house settled 8-12 inches. A settlement study has been done in order to find out if there is ongoing settling of the shaft house from that event.

Phase 1&2

Phase 1 of the restoration was completed in 1996. Corrugated metal was installed on the north and west walls of the shaft house. Phase 2 completed the project with corrugated metal on the south and east walls. Photos below show the shaft house as it was before and after phase 1&2.

 

Comments are closed.